Your town, in plain words

How Centre Hastings uses the money we share.

A clear, checkable guide to Centre Hastings' budget, taxes and council decisions. A municipality of about 4,800 people in Eastern Ontario. Every figure links back to the public record.

Property tax raised in 2025$10Mall property in Centre Hastings70% Town20% County11% SchoolsSee where your tax bill goes →
Town spending, 2025$8.9MAbout $4,079 per household, up 2.2% from 2024.See the money →
Property tax change+4.9%Centre Hastings' own property tax came to $6.9M in 2025, against $6.6M in 2024.What changed →

Where it goes

Most of every dollar supports the everyday town.

Explore every service →
Roads and snow$2.5M · 28%
Police, fire and safety$1.9M · 21%
Water, sewers and garbage$1.7M · 19%
Running the town office$1.2M · 13%
Show all 7 servicesShow fewer
Parks, arena and library$1.1M · 13%
Health$323K · 4%
Planning and business$151K · 2%

Day-to-day spending in 2025, from Centre Hastings' report to the Province.

A fair comparisonHow does Centre Hastings compare?Among 33 similar Ontario towns, Centre Hastings' day-to-day spending per household is on the high side.Centre Hastings is here · 25 of 33, lowest to highestCompare Centre Hastings →

Questions worth asking

A closer look at the numbers.

Each one is a question, not an accusation. Every one lists ordinary reasons it could be true, and the documents it comes from.

All 6 questions
Worth askingRising costs

Why is the new Madoc water tower forecast to cost $2,987,411 more than council approved?

+45.4%forecast cost over the approved $6,573,100 budget for the Madoc standpipe (staff report, September 29, 2026)

A standpipe is a tall tank that stores drinking water and keeps pressure steady. Council approved a budget of $6,573,100 to replace Madoc's. After tenders came in, staff now forecast $9,560,511, which is $2,987,411 (45.4%) over. The province's grant is capped at $4,798,363, so the extra cost falls on the municipality. Staff say the municipality's share goes from $1,774,737 to $4,762,148, to be borrowed and paid back from water and sewer bills and development charges. The town has explained the main reasons in its own report.

Found by reading the town's own documents · 5 sources

Worth askingMoney health

How much debt will Centre Hastings carry once its water and sewer projects are built?

$3,100,000long-term debt at December 31, 2025, up from $72,884 a year earlier, with more borrowing approved or planned

At the end of 2024 the municipality owed $72,884. At the end of 2025 it owed $3,100,000 for the St. Lawrence and Durham Streets work. On September 29, 2026 staff asked council to direct borrowing of $4,762,148 for the new standpipe instead of the $1,774,737 authorized earlier, and council authorized borrowing on May 20, 2026 for a $6,427,500 sewer project. The municipality also owes itself $2,672,451 for projects it paid for from cash before finding a funding source ("unfinanced capital"). Its financial assets, minus what it owes, fell from $4,824,579 to $2,131,922 in 2025. The town has published its debt limit calculation for the first project but we did not find one that includes the newer borrowing.

Found by reading the town's own documents · 7 sources

Good to knowOpenness

Why were several large 2026 water, sewer and bridge contracts awarded without a tender?

$2,973,300single-source award for the Madoc standpipe tank, March 18, 2026, the largest of four no-tender awards in 2026

In 2026 four contracts came to council without competitive bidding: the water tank ($2,973,300 plus HST, March 18), engineering for the St. Lawrence Street West bridge ($82,800, August 5), electrical and controls work at the sewage pumping stations (up to $167,500, plus about $32,500 already done after a failure, August 5), and the Well No. 3 controls ($550,000, September 29). The last two went to the same company. For each one staff explained why, and the policy requires council approval over $125,000. We read the staff recommendations; the September 29 minutes were not yet posted. What the public does not see in one place is how many such awards there are in a year.

Found by reading the town's own documents · 5 sources

Good to knowRising costs

Why did the municipal tax levy rise 8.17% for 2025 and 9.73% for 2026?

+9.73%increase in the municipal tax levy for 2026 ($667,619), after +8.17% for 2025

The levy is the amount the municipality raises from property taxes. It was $6,342,241 for 2024, $6,860,555 for 2025 and $7,528,174 for 2026. For 2026 the municipal tax rate rises 8.06%. On a typical home assessed at $197,000, the total tax bill (including the county and schools) goes up about $230.83, or 6.68%. The municipality has published the reasons.

Found by reading the town's own documents · 5 sources

Show 2 more questionsShow fewer
Good to knowHow decisions are made

What will happen to the money raised for the Madoc pool, now that the pool is permanently closed?

$176,518pool donations reserve at December 31, 2025, down from about $185,518 in September 2025

Council voted on February 19, 2025 to close the Madoc outdoor pool permanently. Community fundraising and the municipality had put $185,518 into a pool reserve fund. In a survey of 439 people, 77% said they want a pool in Centre Hastings, and only 30% supported using the fund for other recreation instead. In October 2025 council decided the municipality will not build, run or fund a new pool, and that the fund stays in place until December 31, 2030 for an outside group's pool project, after which any balance goes to other recreation. People who gave under their own names can ask for refunds.

Found by reading the town's own documents · 5 sources

Good to knowHow decisions are made

Why does the neighbouring township pay about 18% of the Madoc arena's running costs when the old agreement said 30%?

~18%share of arena operating costs paid by Madoc Township in 2026, against 30% in the previous agreement

The Madoc and District Recreation Centre (the arena) is used by people from more than one municipality. The 2026 budget says the Township of Madoc, next door, now contributes about 18% of the arena's operating costs without a formal agreement. The previous formal agreement required 30%. Centre Hastings' own taxpayers cover the rest.

Found by reading the town's own documents · 1 source

Where your tax bill goes

A property tax bill in Centre Hastings pays for three governments. Only part of it goes to the town, and that part is what Centre Hastings council controls.

Tax bill split: Centre Hastings 70%, County or region 20%, Schools 11%
$10Mraised in 2025
  • Centre Hastings70%
  • County or region20%
  • Schools11%
  • Every fact, sourced

    Each number links to the public document it came from. Check it yourself.

  • No accusations

    We ask questions. Every one lists ordinary reasons a number could look odd.

  • Compared fairly

    Towns are only compared with places of a similar size and kind, from the same yearly reports.

Council meetings are open to the public, and councillors answer to you. How to reach Centre Hastings' council · Council Books is free and paid for by readers: support this work.