$3,530,337interest and penalties earned in 2025, against a budget of $470,672
The Town holds a lot of cash. At December 31, 2025 it had $100,300,497 in cash and cash equivalents. The statements show a line called "Interest and penalties". For 2025 the budget was $470,672 and the actual was $3,530,337. For 2024 the budget was $532,964 and the actual was $4,821,340. For 2023 the actual was $4,562,177. So the budget has been a small fraction of the result three years running. The Town's budget slides say interest income can swing and that the Bank of Canada's rate fell from 3.75% in October 2024 to 2.25% in October 2025.
$5,235,000new long-term debt financing proposed for 2026 capital work
A reserve is money set aside for a purpose. At December 31, 2025 the Town's reserves and reserve funds were $104,942,054, and it had $100,300,497 in cash. It also owes $19,500,269 in long-term debt, and in 2025 it issued $1,892,070 of new debt while repaying $2,527,494. The proposed 2026 capital budget plans $5,235,000 of new long-term debt financing, up from $2,670,488 in the 2025 budget. Some of the planned debt is new, such as $1,137,051 for the Town Hall consolidation. The Town says its debt stays within the provincial limit, and the walkthrough shows reserve balances falling over 2026 as projects are paid for.
$2,654,673planning and development spending in 2025, against a budget of $1,925,884
Planning and development covers planning applications, development review and related work. The statements show spending of $2,989,955 in 2023, $1,508,977 in 2024 (budget $1,498,963) and $2,654,673 in 2025 (budget $1,925,884). So 2025 was $728,789 over budget (worked out by us). Inside the 2025 numbers, salaries and benefits were $1,241,082 (2024: $811,567) and materials and supplies $1,267,342 (2024: $558,610). The Town's slides mention an organizational review whose critical changes were approved in 2025, but we did not find a line that explains this department's increase.
$803,003.31extra funding approved on June 15, 2026 for a project budgeted at $3,000,000
The 2026 capital budget put $3,000,000 toward the Maidstone Avenue and Talbot Street intersection. On June 15, 2026 Council awarded the construction for $3,402,282.31 and approved $803,003.31 of extra funding above that $3,000,000. On August 10, 2026 Council awarded the Inspiration Industrial Park servicing tender for $3,016,166.40 and approved $751,362.40 in funding above the approved 2026 capital budget, and a snowplow purchase needed $5,732 more. The Town's summaries say where the extra money comes from: reserves and development charges, and for the industrial park, water and wastewater charges that will be adjusted afterward. We looked only at the summaries for June to September 2026.