Council BooksSouth RiverOntarioSign inSubscribe
Not the full picture. Built from public records, which leave things out.Read by hand, Oct 2026DetailsThis is built from public records, which leave a lot out, and some of it may be wrong or out of date. Check the sources, and tell us if you spot a mistake. What this site can't tell you
Read by hand. We read South River's own documents for this site in October 2026; the Sources page lists which ones. The comparisons with other places still come from the Province's yearly reports.

Questions · 13 so far

Things worth asking about

We read South River's financial reports and meeting minutes, and compared its numbers with 30 similar Ontario towns. These are the things that stood out.

What these are, and what they are not. A question here means a number or practice is unusual, or harder to see than it should be. It does not mean anyone did anything wrong. Most unusual numbers turn out to have ordinary explanations, and every question lists some. The only way to know is to ask.
Needs an answer

Needs an answer

These are unusual enough that residents deserve a clear answer from council.

Worth asking

Worth asking

There may well be a good reason. It is still worth asking what it is.

Worth askingMoney health

What is the $1,081,507 of property the Village is holding to sell, and what will it bring in?

$1,081,507inventories held for resale at December 31, 2025

The Village's balance sheet lists $1,081,507 of "inventories held for resale" at the end of 2025. A year earlier the same line was $1,105,886, up from almost nothing before 2024. In 2025 council also set aside a new reserve called "saleable inventory" of $1,105,000. The statements do not say which properties these are. Council minutes show several small property sales, but the two sale prices we found add up to a small part of the total.

Found by reading the town's own documents · 6 sources

Worth askingMoney health

How is the Village protected on the sale of 281 Hwy 124 that it is helping to finance?

8meetings in a row (worked out by us) whose closed-session agenda named 281 Hwy 124, February 10 to May 26, 2026

On April 28, 2026 council passed one by-law to sell 281 Hwy 124 and another for a vendor take-back mortgage, which means the Village lends part of the price to the buyer. Both by-laws say the terms are in a "Schedule A" that is not posted with them. We could not find the price, the amount lent, the interest rate or the repayment dates. Council's closed-session agenda named the property at eight meetings in a row between February 10 and May 26, 2026 (counted by us).

Found by reading the town's own documents · 4 sources

Worth askingHow decisions are made

What protects the Village if it facilitates a loan of up to $450,000 for the paramedic service's renovation of 309 Hwy 124?

$450,000maximum spending authority for the 309 Hwy 124 renovation, July 14, 2026

On July 14, 2026 council passed a by-law letting staff spend up to $450,000 on renovating 309 Hwy 124 for the district paramedic service. The by-law says the paramedic service will pay the whole cost "through a loan facilitated by the Village of South River". It does not say who is the borrower, who the lender is or what happens if the loan is not repaid.

Found by reading the town's own documents · 3 sources

Worth askingMoney health

How much of the Village's finances depends on the power plant loan it guarantees?

$1,756,211bank loan of the Village-owned power company, guaranteed by the Village, at December 31, 2025

The Village owns South River Power Generation Corporation, which runs a hydroelectric plant. The corporation owes a bank $1,756,211, and the Village has guaranteed that loan. The Village's investment in the corporation is $1,929,679, about 70% of its net financial assets of $2,738,459 (worked out by us). The Village's yearly share of the corporation's profit, $91,852 in 2025 against $305,127 in 2024, is counted as revenue but is not cash.

Found by reading the town's own documents · 4 sources

Worth askingRising costs

Why did South River's property tax go up 8% in 2025?

+8%town property tax, 2024 to 2025

In 2025, South River collected $114K more in its own property tax than in 2024. That is a 8% jump, while prices went up about 2.1%. Only 5 of 30 similar towns raised theirs by more.

Found automatically from the town's financial reports · 3 sources

Worth askingRising costs

Why did the cost of roads and snow grow 73% in 6 years?

+73%roads and snow, 2019 to 2025

South River spent $308K on roads and snow in 2019 and $531K in 2025. Prices only went up about 21% in that time. Only 4 of 30 similar towns had faster growth here.

Found automatically from the town's financial reports · 3 sources

Good to know

Good to know

Background that helps make sense of the rest.

Good to knowRising costs

Why are water costs and water rates rising so sharply from 2026?

18.36%water budget and rates increase approved November 13, 2025

A new five-year agreement with the Ontario Clean Water Agency (OCWA) to run the water plant starts January 1, 2026. Council was told it meant about a 50% rise in OCWA's operating cost, and approved water rates 18.36% higher. The statements show the yearly base price rising from $206,207 to $266,511 (worked out by us: about 29% before extras). Council said OCWA was the lowest bid and that running the plant itself would cost more. Council also hired an engineer for plant upgrades.

Found by reading the town's own documents · 4 sources

Good to knowRising costs

How is the Village keeping the 2026 tax increase to 3.5% when fire, police and water costs jumped?

3.5%overall 2026 tax increase approved July 14, 2026

The Village's share of the shared fire department budget rose 13.1% and its 2026 police costs rose 11%. Water rates rose 18.36%. Council set an overall tax increase of 3.5%. The minutes show a large drop in the Village's share of the community centre and arena budget (55.89%), which the minutes tie to a finished capital project, so some of the room came from one-time spending ending.

Found by reading the town's own documents · 5 sources

Good to knowOpenness

Why is the municipal budget approved in July, and where can residents read it?

July 14, 2026date the 2026 budget was recommended and the tax rate by-law passed

The 2026 budget was recommended and the tax rate by-law passed on July 14, 2026, more than half way through the year. Tax rate by-laws in 2025 and 2024 are dated July 22 and July 23, so this is the Village's usual timing. We did not find the budget document posted on the Village's site.

Found by reading the town's own documents · 3 sources

Good to knowOpenness

Where is the 2025 statement of council pay and expenses?

Council received a "Council Remuneration Report for 2025" on March 24, 2026. We did not find it on the Village's website, so we have not filled in a pay table. The 2024 by-law that sets pay rates is posted.

Found by reading the town's own documents · 1 source

Each question in full

Needs an answerFound automatically from financial reports

Why does South River spend more than most similar towns on council?

$461per home on council, 2025

South River spent about $461 per home on council in 2025. The typical similar town spent $105. Only 2 of 30 similar towns spent more.

Why it matters

Spending more than neighbours is not wrong by itself. It might buy better service. But it is the first place to look for costs that could be lower, such as contracts that were not competitively bid.

It could be because…

  • Geography: more roads, more snow, a bigger area or a landfill of its own.
  • Accounting: some towns record the same cost in a different category.
  • A one-time cost in this year.

Questions you could ask

  1. What makes this cost higher here than in similar towns?
  2. When were the main contracts in this area last put out to competitive tender?

You can ask during the public part of a council meeting, by writing to the clerk, or by contacting your councillors. How to reach council.

Speak for South River? Send us your answer and we will publish it with this question.

The evidence

  1. Council per home: South River $461; typical similar town $105; ranked 3rd highest of 31.

    Ontario Financial Information Return (FIR), 2025, 30 similar municipalities · Schedule 40 and Schedule 2 · archived copy

↑ All questions

Needs an answerFound automatically from financial reports

Why does South River spend more than most similar towns on long-term debt?

$4,087per home on long-term debt, 2025

South River spent about $4,087 per home on long-term debt in 2025. The typical similar town spent $961. Only 2 of 30 similar towns spent more.

Why it matters

Spending more than neighbours is not wrong by itself. It might buy better service. But it is the first place to look for costs that could be lower, such as contracts that were not competitively bid.

It could be because…

  • Geography: more roads, more snow, a bigger area or a landfill of its own.
  • Accounting: some towns record the same cost in a different category.
  • A one-time cost in this year.

Questions you could ask

  1. What makes this cost higher here than in similar towns?
  2. When were the main contracts in this area last put out to competitive tender?

You can ask during the public part of a council meeting, by writing to the clerk, or by contacting your councillors. How to reach council.

Speak for South River? Send us your answer and we will publish it with this question.

The evidence

  1. Long-term debt per home: South River $4,087; typical similar town $961; ranked 3rd highest of 31.

    Ontario Financial Information Return (FIR), 2025, 30 similar municipalities · Schedule 40 and Schedule 2 · archived copy

↑ All questions

Worth askingFound by reading the town's documents

What is the $1,081,507 of property the Village is holding to sell, and what will it bring in?

$1,081,507inventories held for resale at December 31, 2025

The Village's balance sheet lists $1,081,507 of "inventories held for resale" at the end of 2025. A year earlier the same line was $1,105,886, up from almost nothing before 2024. In 2025 council also set aside a new reserve called "saleable inventory" of $1,105,000. The statements do not say which properties these are. Council minutes show several small property sales, but the two sale prices we found add up to a small part of the total.

Why it matters

Over a million dollars, nearly half as much as the Village's cash of $2,485,402, is tied up in property waiting to be sold. Residents should be able to see what it is, what it is expected to fetch, and what happens to the money.

It could be because…

  • Land and buildings the Village decided to sell were moved out of capital assets into held-for-sale, which is how the accounting rules work.
  • The new reserve may simply set aside the expected sale money for future use.
  • Sales take time. The minutes show offers, a listing and a request for proposals in progress.

Questions you could ask

  1. Which properties make up the $1,081,507 held for resale, and what is each expected to sell for?
  2. How much of the sale money has come in since December 31, 2025, and where is it kept?
  3. What is the 'saleable inventory' reserve for, and who decides how it is spent?
  4. Why did the Village record a loss of $795,234 on disposal of assets in 2024?

You can ask during the public part of a council meeting, by writing to the clerk, or by contacting your councillors. How to reach council.

Speak for South River? Send us your answer and we will publish it with this question.

The evidence

  1. The statement of financial position shows "Inventories held for resale" of 1,081,507 at December 31, 2025 and 1,105,886 at December 31, 2024.

    Consolidated Financial Statements, December 31, 2025 · Consolidated Statement of Financial Position, PDF page 5

  2. The 2024 column of the cash flow statement shows "Inventories held for resale" of (1,104,303) and "Proceeds from disposal of tangible capital assets" of 1,082,299. The 2024 column of the statement of operations shows a loss on disposal of tangible capital assets of (795,234). The statements do not name the properties. Worked out by us: the two large 2024 amounts are almost the same size, which suggests property was moved from capital assets to held-for-sale rather than sold for cash. The statements do not say so.

    Consolidated Financial Statements, December 31, 2025 · Consolidated Statement of Cash Flows, PDF page 9; Statement of Operations, PDF page 6

  3. The continuity of accumulated surplus lists a reserve called "Saleable inventory" that went from nothing to 1,105,000 in 2025.

    Consolidated Financial Statements, December 31, 2025 · Note 16, Accumulated Surplus, PDF page 26

  4. On October 14, 2025 council authorized staff to accept an offer of $30,000 plus HST for the sale of 17 Main St.

    Council Meeting minutes, October 14, 2025 · Item 10, In Camera, resolution 301-2025, PDF page 4

  5. On November 25, 2025 council authorized a listing agreement for the vacant property at 68 Riverside Ave "with a listing price of $55,000.00".

    Council Meeting minutes, November 25, 2025 · Resolution 340-2025, PDF page 2

  6. Consolidated Statement of Financial Position: "Cash and cash equivalents (Note 4) $ 2,485,402 $ 1,400,575" (2025, 2024).

    Consolidated Financial Statements, December 31, 2025 · Consolidated Statement of Financial Position, PDF page 5

↑ All questions

Worth askingFound by reading the town's documents

How is the Village protected on the sale of 281 Hwy 124 that it is helping to finance?

8meetings in a row (worked out by us) whose closed-session agenda named 281 Hwy 124, February 10 to May 26, 2026

On April 28, 2026 council passed one by-law to sell 281 Hwy 124 and another for a vendor take-back mortgage, which means the Village lends part of the price to the buyer. Both by-laws say the terms are in a "Schedule A" that is not posted with them. We could not find the price, the amount lent, the interest rate or the repayment dates. Council's closed-session agenda named the property at eight meetings in a row between February 10 and May 26, 2026 (counted by us).

Why it matters

If the Village is the lender it carries the risk that the buyer does not pay. Residents cannot judge that risk without the terms.

It could be because…

  • Selling land and discussing offers is a normal reason to meet in closed session.
  • A vendor take-back mortgage is a common way to sell property that is hard to finance, and it is usually secured on the property itself.
  • The terms may be published once the sale closes.

Questions you could ask

  1. What is the sale price of 281 Hwy 124, and how much of it is being lent by the Village?
  2. What are the interest rate, repayment dates and security for the mortgage?
  3. Will the Village publish the Schedule A terms once the sale closes?

You can ask during the public part of a council meeting, by writing to the clerk, or by contacting your councillors. How to reach council.

Speak for South River? Send us your answer and we will publish it with this question.

The evidence

  1. By-law 31-2026 "to authorize a vendor take back mortgage agreement" for 281 HWY 124 "as in Schedule A attached hereto". The posted by-law has no schedule.

    By-law 31-2026, Mortgage 281 HWY 124 · Title and section 1, PDF page 1

  2. By-law 30-2026 authorizes an agreement for the sale of 281 HWY 124 "as per the terms and conditions in Schedule A". The posted by-law has no schedule and prints no price.

    By-law 30-2026, Sale of 281 HWY 124 · Section 1, PDF page 1

  3. Council passed By-law 30-2026 and By-law 31-2026 on April 28, 2026, and the same agenda lists "281 HWY 124 Sale of Property" as the closed-session item.

    Council Meeting minutes, April 28, 2026 · Item 7 by-laws, PDF pages 3 and 4; item 10, PDF page 5

  4. On November 13, 2025 council authorized staff to negotiate the sale of 281 HWY 124 "as per the terms of RFP-02-2025 as directed in-camera".

    Council Meeting minutes, November 13, 2025 · Resolution 331-2025, PDF page 4

↑ All questions

Worth askingFound by reading the town's documents

What protects the Village if it facilitates a loan of up to $450,000 for the paramedic service's renovation of 309 Hwy 124?

$450,000maximum spending authority for the 309 Hwy 124 renovation, July 14, 2026

On July 14, 2026 council passed a by-law letting staff spend up to $450,000 on renovating 309 Hwy 124 for the district paramedic service. The by-law says the paramedic service will pay the whole cost "through a loan facilitated by the Village of South River". It does not say who is the borrower, who the lender is or what happens if the loan is not repaid.

Why it matters

The Village is signing contracts and spending money up front on a building project that is not its own. If repayment fails, the loss could fall on a village with about $2.5 million in cash.

It could be because…

  • The paramedic service is funded by district levies and may be a reliable payer.
  • The Village may only be passing money through, with the loan agreement protecting it fully.
  • The monthly reports the by-law promises may show every cost is repaid.

Questions you could ask

  1. Who borrows, who lends, and who is legally responsible if the loan is not repaid?
  2. Have the monthly spending reports the by-law requires been presented, and where are they posted?
  3. Will the lease and loan agreements be published?

You can ask during the public part of a council meeting, by writing to the clerk, or by contacting your councillors. How to reach council.

Speak for South River? Send us your answer and we will publish it with this question.

The evidence

  1. By-law 42-2026 says "the total costs will be paid by Parry Sound District Paramedic Service through a loan facilitated by the Village of South River", authorizes spending "to a maximum of $450,000" and says "Monthly spending reports be presented to Council until such time as the loan is started."

    By-law 42-2026, Spending Authority 309 HWY 124 Renovations · Recitals and sections 2 and 3, PDF page 1

  2. On March 10, 2026 council authorized staff "to enter into a Memorandum of Understanding with Parry Sound EMS for the renovation and use of 309 HWY 124 as per the terms attached." The terms are not in the posted minutes.

    Council Meeting minutes, March 10, 2026 · Closed session, resolution 119-2026, PDF page 5

  3. The August 11, 2026 agenda lists a draft "PSEMS Ambulance Base Lease Agreement" under staff reports. We found no minutes for that meeting.

    Council agenda, August 11, 2026 · Item 6.1.2, PDF page 1

↑ All questions

Worth askingFound by reading the town's documents

How much of the Village's finances depends on the power plant loan it guarantees?

$1,756,211bank loan of the Village-owned power company, guaranteed by the Village, at December 31, 2025

The Village owns South River Power Generation Corporation, which runs a hydroelectric plant. The corporation owes a bank $1,756,211, and the Village has guaranteed that loan. The Village's investment in the corporation is $1,929,679, about 70% of its net financial assets of $2,738,459 (worked out by us). The Village's yearly share of the corporation's profit, $91,852 in 2025 against $305,127 in 2024, is counted as revenue but is not cash.

Why it matters

A guarantee means the Village could be asked to repay the bank. The plant's results swing a lot from year to year, so residents should know how well it covers its loan.

It could be because…

  • The loan fell by $235,982 in a year (worked out by us), so it is being paid down.
  • The 2024 profit was higher because of a one-time insurance payment, which the statements explain.
  • A parent guaranteeing a subsidiary's loan is common.

Questions you could ask

  1. Does the power company's cash cover its loan payments every year, including a year with a plant breakdown?
  2. Does council publish the power company's own audited statements?

You can ask during the public part of a council meeting, by writing to the clerk, or by contacting your councillors. How to reach council.

Speak for South River? Send us your answer and we will publish it with this question.

The evidence

  1. "The Corporation has a $1,756,211 (2024 - $1,992,193) term loan with a chartered bank. The loan has been guaranteed by the Municipality."

    Consolidated Financial Statements, December 31, 2025 · Note 7 (continued), PDF page 18

  2. The statement of financial position shows "Investment in South River Power Generation Corporation" of 1,929,679 and net financial assets of 2,738,459.

    Consolidated Financial Statements, December 31, 2025 · Consolidated Statement of Financial Position, PDF page 5

  3. The corporation's revenue was $617,342 in 2025 and $944,128 in 2024, and "During the previous year, the Corporation recognized one-time insurance recovery revenue of $373,867." The Village's share of the annual operating surplus, net of dividends, was $91,852 (2024 - $305,127).

    Consolidated Financial Statements, December 31, 2025 · Note 7, PDF pages 17 and 18

  4. The July 14, 2026 agenda lists "SRPGC 2025 Audited Financial Statements" among the accounts reports, and council received those reports.

    Council Meeting minutes, July 14, 2026 · Item 5.1.4 and resolution 248-2026, PDF page 1

↑ All questions

Worth askingFound automatically from financial reports

Why did South River's property tax go up 8% in 2025?

+8%town property tax, 2024 to 2025

In 2025, South River collected $114K more in its own property tax than in 2024. That is a 8% jump, while prices went up about 2.1%. Only 5 of 30 similar towns raised theirs by more.

Why did South River's property tax go up 8% in 2025?
$1.6M
Show as a table
YearTown property tax
2019$1.1M
2020$1.1M
2021$1.2M
2022$1.3M
2023$1.4M
2024$1.4M
2025$1.6M

Why it matters

A big one-year jump usually means something changed: a new cost, a service that grew, savings being rebuilt, or a problem from earlier years being paid for now. Residents should be able to see exactly which. Spread across every home, it is about $224 more each year.

It could be because…

  • Costs the town cannot control went up, such as policing, insurance or county charges.
  • The town kept taxes too low in earlier years and is catching up.
  • The town is rebuilding savings or paying for a big project like a bridge or equipment.

Questions you could ask

  1. What were the three biggest reasons for the 2025 increase, in dollars?
  2. Is a similar increase planned for next year?

You can ask during the public part of a council meeting, by writing to the clerk, or by contacting your councillors. How to reach council.

Speak for South River? Send us your answer and we will publish it with this question.

The evidence

  1. Town property tax: $1,441,219 in 2024, $1,555,402 in 2025.

    Ontario Financial Information Return (FIR), 2019 to 2025 · Schedule 10, line 9940 · archived copy

  2. Typical increase among 30 similar Ontario towns: 4.7%. South River ranks 6th highest.

    Ontario Financial Information Return (FIR), 2025, 30 similar municipalities · Schedule 10, line 9940 · archived copy

  3. Prices (inflation) rose 2.1% over the same year.

    Statistics Canada CPI, table 18-10-0005-01 · archived copy

↑ All questions

Worth askingFound automatically from financial reports

Why did the cost of roads and snow grow 73% in 6 years?

+73%roads and snow, 2019 to 2025

South River spent $308K on roads and snow in 2019 and $531K in 2025. Prices only went up about 21% in that time. Only 4 of 30 similar towns had faster growth here.

Why did the cost of roads and snow grow 73% in 6 years?
+73%
Show as a table
YearRoads and snowPrices (inflation)
2019+0%+0%
2020+4%+1%
2021+6%+4%
2022+11%+11%
2023+20%+16%
2024+51%+18%
2025+73%+21%

Change since the first year shown. The grey line is how much prices rose overall, for comparison.

Why it matters

When one area grows much faster than prices, it is either doing more (which may be great) or paying more for the same thing. Residents deserve to know which.

It could be because…

  • The town added a service, a building or staff that residents asked for.
  • Costs were moved from another area, so the total did not really change.
  • Accounting rules changed how costs are sorted.
  • Large one-time costs, like a study, lawsuit or repair, landed in one year.

Questions you could ask

  1. What did the extra $224K a year pay for?
  2. Why did snow ploughing go from $179K to $301K?
  3. Was each increase approved by council as a separate decision, or did it happen through the yearly budget?

You can ask during the public part of a council meeting, by writing to the clerk, or by contacting your councillors. How to reach council.

Speak for South River? Send us your answer and we will publish it with this question.

The evidence

  1. Roads and snow: 2019 $308K, 2020 $319K, 2021 $326K, 2022 $340K, 2023 $368K, 2024 $464K, 2025 $531K.

    Ontario Financial Information Return (FIR), 2019 to 2025 · Schedule 40 · archived copy

  2. Biggest driver: Snow ploughing, from $179K to $301K.

    Ontario Financial Information Return (FIR), 2019 to 2025 · Schedule 40 · archived copy

  3. Typical growth among similar towns: 30%. South River ranks 5th of 31.

    Ontario Financial Information Return (FIR), 2025, 30 similar municipalities · Schedule 40 · archived copy

↑ All questions

Good to knowFound by reading the town's documents

Why are water costs and water rates rising so sharply from 2026?

18.36%water budget and rates increase approved November 13, 2025

A new five-year agreement with the Ontario Clean Water Agency (OCWA) to run the water plant starts January 1, 2026. Council was told it meant about a 50% rise in OCWA's operating cost, and approved water rates 18.36% higher. The statements show the yearly base price rising from $206,207 to $266,511 (worked out by us: about 29% before extras). Council said OCWA was the lowest bid and that running the plant itself would cost more. Council also hired an engineer for plant upgrades.

Why it matters

Water is paid for by the households that use it, and the increase is large. The Village gave its reasons, so this is context rather than a concern.

It could be because…

  • The old 2016 contract price had not kept up with costs, so the reset is large.
  • Council reports the work was tendered and OCWA's bid was the lowest.
  • Chemical costs are now billed separately each quarter, which changes how the monthly invoice compares.

Questions you could ask

  1. How many bids did the water operating tender receive, and what were they?
  2. What will the plant upgrades cost in total, and how much is covered by the provincial grant versus water rates?
  3. Will the 2026 water budget be posted?

You can ask during the public part of a council meeting, by writing to the clerk, or by contacting your councillors. How to reach council.

Speak for South River? Send us your answer and we will publish it with this question.

The evidence

  1. Council discussed "a potential rate increase of 22% to compensate for the 50% operating cost increase from OCWA beginning January 2026", said it "was tendered out and OCWA was the lowest option", and noted that working alone "would be more costly and no other community participated in the tender process."

    Council Meeting minutes, October 28, 2025 · Item 5.1.1, 2026 Water Budget and Billing, PDF page 1

  2. Council approved "the 2026 Water Budget and Rates with a 18.36% increase as attached." The attached budget is not in the posted minutes.

    Council Meeting minutes, November 13, 2025 · Resolution 320-2025, PDF page 1

  3. Note 13 says that since 2020 "the annual base price is $206,207" plus adjustments, and that a new agreement effective January 1, 2026 has "an annual base price of $266,511 in the first year plus a CPI adjustment annually."

    Consolidated Financial Statements, December 31, 2025 · Note 13, Contractual Obligations, PDF page 22

  4. Council awarded RFP 01-2026 for engineering services for water treatment plant upgrades "at the upset limit cost of $179,355 excluding HST".

    Council Meeting minutes, March 10, 2026 · Item 6.1, resolution 102-2026, PDF page 2

↑ All questions

Good to knowFound by reading the town's documents

How is the Village keeping the 2026 tax increase to 3.5% when fire, police and water costs jumped?

3.5%overall 2026 tax increase approved July 14, 2026

The Village's share of the shared fire department budget rose 13.1% and its 2026 police costs rose 11%. Water rates rose 18.36%. Council set an overall tax increase of 3.5%. The minutes show a large drop in the Village's share of the community centre and arena budget (55.89%), which the minutes tie to a finished capital project, so some of the room came from one-time spending ending.

Why it matters

Residents see one number, the tax increase, but the lasting pressures are in fire, police and water. The arena drop does not repeat.

It could be because…

  • The minutes say fire costs went up partly because a grant that helped in 2025 does not continue in 2026.
  • Council records the arena's capital project ended in 2025 with savings left over.
  • Police costs are set by others and not within the Village's control.

Questions you could ask

  1. What did the 3.5% increase assume for fire, police and water costs in 2027?
  2. Which one-time savings helped hold the 2026 increase down?

You can ask during the public part of a council meeting, by writing to the clerk, or by contacting your councillors. How to reach council.

Speak for South River? Send us your answer and we will publish it with this question.

The evidence

  1. The draft fire budget proposed "an increase of $35,328 (14.92%) for each municipality". The draft arena budget showed "a -$501,367 (-90.6%) capital budget decrease" after its capital project ended.

    Committee of the Whole minutes, January 28, 2026 · Item 3, PDF page 1

  2. Council supported the fire budget "in the amount of $534,286 with South River's contribution being $267,143 a 13.1% increase from 2025" and the community centre budget "in the amount of $428,088 with South River's contribution being $188,851 a 55.89% decrease from 2025."

    Council Meeting minutes, March 24, 2026 · Resolutions 127-2026 and 128-2026, PDF page 1

  3. Council authorized payment of "the 2026 OPP costs of $282,349 an 11% increase over 2025".

    Council Meeting minutes, February 10, 2026 · Resolution 35-2026, PDF page 1

  4. Council resolved to "recommend the 2026 Budget and appropriate tax by-law be brought forward with an overall tax increase of 3.5%."

    Council Meeting minutes, July 14, 2026 · Resolution 252-2026, PDF page 3

  5. Resolution 320-2025: "BE IT RESOLVED THAT the Council of the Village of South River does hereby approve the 2026 Water Budget and Rates with a 18.36% increase as attached." Carried.

    Council Meeting minutes, November 13, 2025 · Resolution 320-2025, PDF page 1

↑ All questions

Good to knowFound by reading the town's documents

Why is the municipal budget approved in July, and where can residents read it?

July 14, 2026date the 2026 budget was recommended and the tax rate by-law passed

The 2026 budget was recommended and the tax rate by-law passed on July 14, 2026, more than half way through the year. Tax rate by-laws in 2025 and 2024 are dated July 22 and July 23, so this is the Village's usual timing. We did not find the budget document posted on the Village's site.

Why it matters

A budget is how residents see what taxes will pay for. If it is only in the minutes as a total percentage, they cannot check it.

It could be because…

  • Interim tax bills in January cover the early months, and the Village waits for school, county and shared-service numbers.
  • The budget may be available at the office on request.

Questions you could ask

  1. Will the Village post its adopted municipal budget each year?
  2. Could the budget be adopted earlier, so residents can comment before most of the year has passed?

You can ask during the public part of a council meeting, by writing to the clerk, or by contacting your councillors. How to reach council.

Speak for South River? Send us your answer and we will publish it with this question.

The evidence

  1. On January 13, 2026 council passed By-law 3-2026, "to authorize the 2026 Interim Tax Levy".

    Council Meeting minutes, January 13, 2026 · Item 7 by-laws, PDF pages 2 and 3

  2. On June 23, 2026 "Council reviewed the proposed municipal budget an O Reg report and recommended both come forward for the next meeting of Council."

    Council Meeting minutes, June 23, 2026 · Item 5.1, PDF page 1

  3. On July 14, 2026 council passed By-law 40-2026, "to provide for the adoption of tax rates and to further provide for penalty and interest for the year 2026".

    Council Meeting minutes, July 14, 2026 · Resolution 254-2026, PDF page 3

↑ All questions

Good to knowFound by reading the town's documents

Where is the 2025 statement of council pay and expenses?

Council received a "Council Remuneration Report for 2025" on March 24, 2026. We did not find it on the Village's website, so we have not filled in a pay table. The 2024 by-law that sets pay rates is posted.

Why it matters

Ontario councils report each member's pay and expenses every year. Residents should be able to read it.

It could be because…

  • It may be posted somewhere we did not look, or available at the office.
  • The report may be in the March 24 agenda package, which is not posted.

Questions you could ask

  1. Will the Village post the 2025 council remuneration report?

You can ask during the public part of a council meeting, by writing to the clerk, or by contacting your councillors. How to reach council.

Speak for South River? Send us your answer and we will publish it with this question.

The evidence

  1. The March 24, 2026 minutes list "Council Remuneration Report for 2025" as item 5.1.3, and council received reports 1 to 4.

    Council Meeting minutes, March 24, 2026 · Item 5.1.3 and resolution 130-2026, PDF page 1

↑ All questions

Good to knowFound automatically from financial reports

Why does South River spend more than most similar towns on snow ploughing?

$590per home on snow ploughing, 2025

South River spent about $590 per home on snow ploughing in 2025. The typical similar town spent $142. None of the 30 similar towns spent more.

Why it matters

Spending more than neighbours is not wrong by itself. It might buy better service. But it is the first place to look for costs that could be lower, such as contracts that were not competitively bid.

It could be because…

  • Geography: more roads, more snow, a bigger area or a landfill of its own.
  • Accounting: some towns record the same cost in a different category.
  • A one-time cost in this year.

Questions you could ask

  1. What makes this cost higher here than in similar towns?
  2. When were the main contracts in this area last put out to competitive tender?

You can ask during the public part of a council meeting, by writing to the clerk, or by contacting your councillors. How to reach council.

Speak for South River? Send us your answer and we will publish it with this question.

The evidence

  1. Snow ploughing per home: South River $590; typical similar town $142; ranked 1st highest of 31.

    Ontario Financial Information Return (FIR), 2025, 30 similar municipalities · Schedule 40 and Schedule 2 · archived copy

↑ All questions