Why did the W.J. Henderson Community Centre project grow from $49,500,000 to $59,400,000, and what is still in dispute?
$59,400,000estimated cost at completion (March 2026), against $49,500,000 approved in November 2023
In November 2023, council approved rebuilding the W.J. Henderson Community Centre (the arena and a new pool) for $49,500,000. In March 2026 the Township told council that the job will cost an estimated $59,400,000, which is $9,900,000 more. The Township published a long, itemized explanation: ground and building problems nobody could see in advance, extras the Township asked for, and a price on the contract that went up. It also lists $1,450,000 of contractor costs as "disputed", which is not settled.
Found by reading the town's own documents · 6 sources